Mercer County PSD Meeting Minutes November 2025

MERCER COUNTY PUBLIC SERVICE DISTRICT โ€“ MONTHLY BOARD MEETING

NOVEMBER 6, 2025

The Mercer County Public Service District met at 241 Mercer Springs Road, Princeton, WV. The meeting was opened by Chairman Kennett at 10:00 a.m. following a prayer by Stacy Fowler.


BOARD & PROJECT UPDATES

  • Administrative: Bill Winfrey was absent; Chairman Kennett provided the update.
  • Rt. 19 Agreements: Agreements are completed. A message was sent to Bill Winfrey regarding the right-of-way for the building in Lake Bottom.
  • Electrical: Vest Electric has completed the electrical install, with inspection occurring on November 5, 2025. Quoted work will be completed soon.
  • McComas Project: Design is complete. There are 36 total easements; 15 are complete and title work is finished for those. All permits are in place, though there is no DOH Bond yet.
  • Matoaka: This project is almost finished. A spreadsheet for final expenditures will be sent out by Jack Ramsey. A remaining balance of $2,767.67 may be used for safety equipment pending review of a submitted list.

REGIONAL PROJECT & INFRASTRUCTURE

  • Regional Sewer: EL Robinson has completed Phase A1 and A1A; they are currently waiting on EPA comments and signed permits. Design is complete.
  • Rt. 19 Bridge Crossings: Currently in a holding pattern awaiting funding. Commission President Bill Archer met with Parkways; they request designs. Discussion regarding hanging a new 6-inch line to connect projects is ongoing.
  • Pocahontas Water Replacement: Bids open on December 14. There was discussion regarding contractor licensing requirements between West Virginia and Virginia.
  • Cornbread Ridge & Brickyard: Cornbread Ridge is being pushed forward by Commissioner Puckett, while funding is still being sought for Brickyard.
  • Oakvale: Connection costs are currently too high ($500,000 per customer) to justify service at this time.

AGENCY & FUNDING UPDATES

  • Furloughs: DEP and EPA workers are currently furloughed with no update. Stacy Fowler noted that funding is secure until the end of March 2026.
  • Region One: Assisted with McComas flood notices published recently.
  • Right-of-Ways: Emerald Energy of Kentucky will handle right-of-ways. The Board expressed that the cost of $1,350.00 per easement is very high.
  • IJDC: The current funding cap is $350,000; the District has asked for this cap to be reviewed.

LASHMEET BOUNDARY EXTENSION

  • Water & Sewer: Extension is for water only as the PSD already controls sewer rights. American Waterโ€™s involvement is needed for billing and PSC rate establishment. This was not on the agenda for today so no formal action was taken.

PERSONNEL CHANGES

  • New Hire: Falicay Hammack joined as a Part Time employee at the Matoaka Plant. She will be processing for OIT.

FINANCIALS & ADJOURNMENT

  • Motions: Mike moved and Leo seconded to accept McComas contracts, invoices, and Thomas & Litton drawdowns; the motion was approved.
  • Final Check: A final check of $170.00 to Region One will close the project account.

Meeting Adjourned Next Meeting: December 4th, 2025